In this project in Caramos, Felgueiras, we followed the execution of a structural steel frame for a family home from the study and design phase through to fabrication and on-site installation.
The solution was developed in S275JR steel and included a 9-metre cantilever, approximately 36 tonnes of steel and 350 m² of composite slab. This configuration made it possible to meet the structural requirements of the house, ensuring strength, stability and load-bearing capacity.
We finished the structure with RAL 7016 paint, ensuring steel protection and an appearance compatible with the architectural context of the project.
Technical details
Material
S275JR
Finish
RAL 7016 paint
Services involved
Gallery
Technical details
Material
S275JR
Finish
Finish
Services involved